How long is the planning horizon for an Airport Master Plan?

Study for the AAAE Certified Member Test. Use flashcards and multiple choice questions, complete with hints and explanations. Get ready for your exam success!

The planning horizon for an Airport Master Plan is set at 20 years. This timeframe is deemed appropriate because it allows for a comprehensive evaluation of air transportation needs while considering potential demographic, economic, and infrastructure developments. A 20-year outlook strikes a balance between being long enough to plan for significant changes and developments in aviation and the surrounding community, but it remains practical for making actionable decisions.

Planning for too short of a period may overlook necessary long-term investments and strategic direction, while extending the horizon beyond 20 years could make the forecasts and planning less relevant due to changing circumstances. This duration aligns with industry standards, enabling airports to effectively strategize and secure funding while remaining adaptable to future trends in air travel and technology.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy